Scheldt Bridge

Project name

Scheldt Bridge

Year

2020

Location

Temse, Belgium

Application

Concrete Topping

Advantages and Benefits

Using synthetic fibres as alternative for steel mesh made the job much quicker, safer and more environmental friendly.

Company

ADFIL

Products

Durus EasyFinish – Crackstop

The Scheldt bridge in Temse is the longest bridge over water with a combined traffic of railways and cars. For the renovation the contractor was asked to install a crack-free and watertight pressure layer between the constructive concrete and the asphalt top layers.

The 4kg/m³ dosage of macro #synthetic #fibres and an extra 600g of micro synthetic fibres made this an efficient and easy job with good results.

This solution replaced a steel mesh and eliminated the risk for corrosion. The variable thickness of the pressure layer would have make the correct installation of a steel mesh almost impossible.